Canadian Natural Resources Limited Announces Third Quarter 2008
Update on the Progress of the Horizon Oil Sands Project
CALGARY, ALBERTA--(Marketwire - November 06, 2008) - Canadian Natural
Resources Limited's ("Canadian Natural" or the "Company") (TSX: CNQ)
(NYSE: CNQ) is pleased to provide its regular quarterly update on the
Horizon Oil Sands Project ("Horizon Project" or the "Project").
Steve Laut, President and Chief Operating Officer of Canadian Natural
commented, "Canadian Natural continues with the completion of the
construction, commissioning and staged start up of the Horizon
Project where we have made significant progress. We are encountering
and overcoming challenges in our drive to complete the Project and
commence production of Synthetic Crude Oil. These challenges are
primarily related to commissioning and startup of the more complex
components of the Project. We have resolved these challenges in the
Delayed Coker, the Co-generation Plant and the Hydrogen Plant. We are
currently in the process of resolving outstanding matters in the
Naphtha Hydrotreater and Gas Oil Hydrotreater in the Secondary
Upgrading process. We continue to target first Synthetic Crude Oil
production in 2008, but recognize that there must not be any further
delays in the completion or commissioning of these complex components
of the Project. The construction and operations teams in all areas
continue to work together to resolve issues and continue to test and
prepare for operations."
Canadian Natural is continuing with the staged start up of the
Horizon Project. The seven stages to the start up of the Horizon
Project, as outlined in the second quarter update release, and the
associated targeted start up dates are as follows:
Stage 1 - Mining
- The Mining Operation is ready and continues to move overburden. The
mining team has already delivered over 300,000 tonnes of mined oil
sands to the Plant for test purposes.
Stage 2 - Steam Supply
- As previously targeted, the utility plants have been supplying low,
medium and high pressure steam for commissioning and start up
purposes since July of this year.
Stage 3 - Bitumen Crude Oil Production
- The Bitumen Crude Oil Production operations are fully commissioned
except for Froth Treatment. The delays encountered in Froth Treatment
have now been resolved. The necessary re-work has been completed and
commissioning is well underway. As previously targeted, first bitumen
crude oil production of approximately 160,000 barrels for test
purposes was achieved in September.
Stage 4 - Electricity Generation
- The Co-generation Plant has been producing steam since late July.
Electricity generation has been commissioned and is ready for
operations.
Stage 5 - Sulphur Plant/Sour Gas Treating
- The Sulphur Plant is complete and being turned over to operations
for commissioning.
Stage 6 - Partially Upgraded Crude Oil Production
- The Delayed Coker / Diluent Recovery Unit Plants were completed in
late October and have been turned over to operations for
commissioning and are currently circulating diesel and waiting for
Secondary Upgrading (Hydrotreaters) to start up.
Stage 7 - 34 degreesAPI, Light Sweet Synthetic Crude Oil Production
- The Naphtha Hydrotreating Plant (Plant 41) is completed and
currently being commissioned.
- The Gas Oil Hydrotreating Plant (Plant 43) is completing electrical
heat tracing and insulation concurrent with commissioning.
- With an estimated start up capacity of 70,000 bbl/d, first delivery
of 34 degrees API, light sweet SCO to the sales pipeline is currently
targeted for late in the fourth quarter of 2008.
- The Distillate Hydrotreating Plant (Plant 42) is mechanically
complete except for electrical heat tracing and insulation. First
product output through Plant 42 is currently targeted for the latter
part of Q1/09 enabling production to start ramping up to targeted
facility capacity of 110,000 bbl/d.
- Targeted production ramp up would see 50-60% of facility capacity
by the end of Q1/09 and reach full targeted facility capacity later
in 2009.
Commenting on third quarter progress, Real Doucet, Senior Vice
President, Oil Sands, stated "The majority of the processing plants
are either fully commissioned or well into commissioning. The
remaining work is being carefully managed, to ensure a successful
project by having all the necessary systems operational for cold
weather. The safety and well-being of our contractors and operations
staff remains a priority. Our on-site manpower is ramping down as we
have reduced our construction workforce by over 50% during Q3/08 to
approximately 2,500 tradesmen currently on site. The necessary
operators required for start up and a strong management team are all
in place."
A high level overview of progress by major plant facility at the
Horizon Project is as follows:
- Mining - Completed, ready for oil sands mining operation, continues
to move overburden
- Ore Preparation Plant - Completed, ready for operation
- Hydrotransport - Completed, ready for operation
- Piperack - Completed, live and operational
- Extraction - Completed, ready for operation
- Froth Treatment - Completed, in commissioning and testing
- Delayed Coker / Diluent Recovery Unit - Completed, circulating
diesel and ready for operation
- Co-generation - Completed, producing steam and power
- Sulphur Plant - Completed, turned over to operations for
commissioning and testing
- Tankage - Completed, ready for operation
- Main Control Room - Completed, live and operational
- Utilities & Services - Completed, live and operational
- SCO Pipeline (third party owned and operated) - Completed, ready
for operation
- Hydrogen Plant - Completed, turned over to operations for
commissioning and testing
- Hydrotreaters - Plant 41 has been completed and turned over to
operations for commissioning and testing. Plant 43 is completing
electrical heat tracing and insulation while starting commissioning.
Plant 42 is mechanically complete with electrical heat tracing and
insulation to be completed before turning over to operations for
commissioning and testing.
The delays experienced and extended commissioning schedule has lead
to an increase of $441 million to the Project forecast construction
costs. This results in the revised total cost estimate for Phase 1 of
the Horizon Project to be approximately $9.7 billion. The targeted
on-stream cost estimate is $88,200 bbl/d capacity, including the
benefits of the significant pre-build capital invested for future
phases. Although Canadian Natural is disappointed with the increase
to the overall targeted project cost, the Company wants to ensure
that it is done right, with the safety of the staff and contractors,
along with the quality of the operation, always in mind.
A picture gallery providing visual updates on construction progress
is available on the Company's website
(http://www.cnrl.com/horizon/about_horizon/photo_gallery.html).
The Company's results for the third quarter of 2008 will be released
on November 6th, 2008. A conference call will be held on that day at
7:00 a.m. Mountain Daylight Time, 9:00 a.m. Eastern Daylight Time.
Canadian Natural is a senior oil and natural gas production company,
with continuing operations in its core areas located in Western
Canada, the U.K. portion of the North Sea and Offshore West Africa.
SPECIAL NOTE REGARDING FORWARD-LOOKING STATEMENTS
Certain statements in this document or documents incorporated herein
by reference constitute forward-looking statements or information
(collectively referred to herein as "forward-looking statements")
within the meaning of applicable securities legislation.
Forward-looking statements can be identified by the words "believe",
"anticipate", "expect", "plan", "estimate", "target", "continue",
"could" "intend", "may", "potential", "predict", "should", "will",
"objective", "project", "forecast", "goal", "guidance", "outlook",
"effort" "seeks", "schedule" or expressions of a similar nature
suggesting future outcome or statements regarding an outlook.
Statements relating to "reserves" are deemed to be forward-looking
statements as they involve the implied assessment based on certain
estimates and assumptions that the reserves described can be
profitably produced in the future. There are numerous uncertainties
inherent in estimating quantities of proved crude oil and natural gas
reserves and in projecting future rates of production and the timing
of development expenditures. The total amount or timing of actual
future production may vary significantly from reserve and production
estimates. In addition, these statements are not guarantees of future
performance and are subject to certain risks and the reader should
not place undue reliance on these forward-looking statements as there
can be no assurance that the plans, initiatives or expectations upon
which they are based will occur.
The forward-looking statements are based on current expectations,
estimates and projections about Canadian Natural Resources Limited
(the "Company") and the industry in which the Company operates, which
speak only as of the date such statements were made or as of the date
of the report or document in which they are contained and are subject
to known and unknown risks, uncertainties and other factors that
could cause the actual results, performance or achievements of the
Company to be materially different from any future results,
performance or achievements expressed or implied by such
forward-looking statements. Such factors include, among others:
general economic and business conditions which will, among other
things, impact demand for and market prices of the Company's
products; volatility of and assumptions regarding crude oil and
natural gas prices; fluctuations in currency and interest rates;
assumptions on which the Company's current guidance is based;
economic conditions in the countries and regions in which the Company
conducts business; political uncertainty, including actions of or
against terrorists, insurgent groups or other conflict including
conflict between states; industry capacity; ability of the Company to
implement its business strategy, including exploration and
development activities; impact of competition; the Company's defense
of lawsuits; availability and cost of seismic, drilling and other
equipment; ability of the Company and its subsidiaries to complete
its capital programs; the Company's and its subsidiaries' ability to
secure adequate transportation for its products; unexpected
difficulties in mining, extracting or upgrading the Company's bitumen
products; potential delays or changes in plans with respect to
exploration or development projects or capital expenditures; ability
of the Company to attract the necessary labour required to build its
thermal and oil sands mining projects; operating hazards and other
difficulties inherent in the exploration for and production and sale
of crude oil and natural gas; availability and cost of financing; the
Company's and its subsidiaries' success of exploration and
development activities and their ability to replace and expand crude
oil and natural gas reserves; timing and success of integrating the
business and operations of acquired companies; production levels;
imprecision of reserve estimates and estimates of recoverable
quantities of crude oil, bitumen, natural gas and liquids not
currently classified as proved; actions by governmental authorities;
government regulations and the expenditures required to comply with
them (especially safety and environmental laws and regulations and
the impact of climate change initiatives on capital and operating
costs); asset retirement obligations; the adequacy of the Company's
provision for taxes; and other circumstances affecting revenues and
expenses. Certain of these factors are discussed in more detail under
the heading "Risk Factors".
The Company's operations have been, and at times in the future may be
affected by political developments and by federal, provincial and
local laws and regulations such as restrictions on production,
changes in taxes, royalties and other amounts payable to governments
or governmental agencies, price or gathering rate controls and
environmental protection regulations. Should one or more of these
risks or uncertainties materialize, or should any of the Company's
assumptions prove incorrect, actual results may vary in material
respects from those projected in the forward-looking statements. The
impact of any one factor on a particular forward-looking statement is
not determinable with certainty as such factors are dependent upon
other factors, and the Company's course of action would depend upon
its assessment of the future considering all information then
available.
Readers are cautioned that the foregoing list of important factors is
not exhaustive. Unpredictable or unknown factors not discussed in
this report could also have material adverse effects on
forward-looking statements. Although the Company believes that the
expectations conveyed by the forward-looking statements are
reasonable based on information available to it on the date such
forward-looking statements are made, no assurances can be given as to
future results, levels of activity and achievements. All subsequent
forward-looking statements, whether written or oral, attributable to
the Company or persons acting on its behalf are expressly qualified
in their entirety by these cautionary statements. Except as required
by law, the Company assumes no obligation to update forward-looking
statements should circumstances or Management's estimates or opinions
change.
Contacts:
Canadian Natural Resources Limited
Allan P. Markin
Chairman
(403) 514-7777
(403) 514-7888 (FAX)
Canadian Natural Resources Limited
John G. Langille
Vice-Chairman
(403) 514-7777
(403) 514-7888 (FAX)
Canadian Natural Resources Limited
Steve W. Laut
President and Chief Operating Officer
(403) 514-7777
(403) 514-7888 (FAX)
Canadian Natural Resources Limited
Douglas A. Proll
Chief Financial Officer and Senior Vice-President, Finance
(403) 514-7777
(403) 514-7888 (FAX)
Canadian Natural Resources Limited
Corey B. Bieber
Vice-President, Finance and Investor Relations
(403) 514-7777
(403) 514-7888 (FAX)
Canadian Natural Resources Limited
2500, 855 - 2nd Street S.W.
Calgary, Alberta T2P 4J8
Email: ir@cnrl.com
Website: www.cnrl.com
This announcement was originally distributed by Hugin. The issuer is
solely responsible for the content of this announcement.